Page 1
Oct 24, 2026
To: Sales engineer, Molder A
We are developing the plastic-base snap mousetrap and are asking a small number of suppliers to quote the parts below. The drawings and CAD files are attached under a mutual NDA.
For each part: piece price at the first-order and annual quantities, tooling cost and type, cavities, tool life, lead time for tooling and for parts, and what is included (inspection, packaging, freight).
Reply to [email protected].
Page 2
| Part no. | Part | What it is | Per unit | Drawing / CAD | Make or buy |
|---|---|---|---|---|---|
| MT-001 | Plastic base | Nylon 6/6 base with the bait cup, finger guard and spring post molded in. Wall 1.8 mm, draft 1 degree. | 1 each | CAD rev X3 (STEP) and a drawing with critical features | make |
| MT-002 | Trigger plate | Nylon 6/6 pedal with the bait spike molded on. Its own small mold. | 1 each | CAD rev X3 (STEP) | make |
Page 3
These come from the failures that could hurt someone or stop the product working. They are marked on the drawings.
| Failure or feature | Why it matters | |
|---|---|---|
| F1 | Base cracks at the spring seat | Severity 8 |
| Add a short rib at the spring seat | design feature to hold | |
| Use an engineered resin | design feature to hold | |
| F11 | A finger stays in the path of the bail while setting | Severity 9 |
| Mold a set-from-the-side mark | design feature to hold | |
| Mold a finger guard beside the bail | design feature to hold |
Parts in bulk cartons by part number; label with part number and lot
Page 4
| Tooling ownership | The inventor owns the molds and can move them |
| Payment terms asked | 50% of tooling at order, 50% at first-article approval; parts net 30 |
| Confidentiality | Signed mutual NDA before CAD is sent |
| By | Milestone |
|---|---|
| Apr 30, 2027 | First shipment to a distributor |
| Dec 15, 2026 | Design frozen (risk actions in the CAD) |
| Jan 15, 2027 | Molds ordered |
| Mar 15, 2027 | First articles approved |
| Nov 30, 2026 | Buyer feedback from 3 distributors |
| Oct 22, 2026 | Spring supplier confirmed |
| Oct 29, 2026 | Base mold quote in hand |
Last page
Get firm quotes for the base and trigger plate molds and parts, including a 2-cavity family mold option
No tooling order until the numbers close; no tool we can't move
| Question | Answer |
|---|---|
| What volume is this really? | 5,000 for the first order, 50,000 a year planned for two years; we'll confirm with distributor orders. |
| Who pays for the tool and when? | We do: half at order, half at first-article approval. |
| What tolerances matter? | The spring seat, the bail pivot holes and the finger guard; the rest is cosmetic. They're marked on the drawing. |
| What resin? | Nylon 6/6 for both parts; open to a suggestion if it molds better. |
| Line every quote up on | Molder A |
|---|---|
| Piece price at first order and at annual volume | |
| Tooling: cost, type (steel or aluminum), cavities, life in shots | |
| Who owns the tool, and can it move | |
| Lead time: tooling, first articles, production | |
| What's included: inspection, packaging, freight | |
| Payment terms |
Each quote goes on the cost sheet as a quote with its date, replacing the placeholder (today's placeholder tooling: $107,000).
| Today | Note | |
|---|---|---|
| Legal name | Not formed yet | Forming a single-owner LLC is with the Office Manager Bot (business risk B5). |
| Entity | Planned: single-owner LLC | |
| Tax ID (EIN) | Not yet | Needed for a W-9 and a business bank account. Free from the IRS once the LLC exists. |
| W-9 for vendor setup | After the tax ID | |
| Business bank account | Not yet | |
| Product liability insurance | Quotes requested | Buyers often ask for a certificate of $1 million or more naming them. Illustrative. |
| UPC / GTIN barcodes | Not yet | License from GS1 before packaging is printed. Illustrative. |
| Rules that apply | To check: EPA rules for pest-control devices | A mechanical trap is a pest-control device; check EPA labeling and establishment rules before the first shipment. Illustrative. |
This packet, minus this page.
Record what was said in this folder; add any signal to market-evidence.csv; update contacts.csv with the next step and date; put every promise on the action log (sop-meeting-prep.txt step 8).