A.N. Creation Office · Project record

Schedule

Critical path: Buyer feedback from 3 distributors → Design frozen (risk actions in the CAD) → Molds ordered (only if the numbers close) → First articles approved → First shipment to a distributor.

The end moves: First shipment to a distributor is forecast 7 days after the charter's date. Recover time on the critical path, or the inventor accepts the new date through a change notice.

IDMilestoneDepends onDays afterPlanned (charter)ForecastActualSlip, daysCriticalNotes
M1Spring supplier confirmed2026-10-222026-10-220Waiting on the supplier
M2Base mold quote in hand2026-10-292026-10-290Due from Molder A
M3Buyer feedback from 3 distributors2026-11-302026-12-15+15yesIllustrative: only one buyer meeting is set so far (10-28); two more distributors to approach
M4Design frozen (risk actions in the CAD)M1 M2 M3142026-12-152026-12-29+14yesTwo weeks after the last input to fold in the quotes and the buyer feedback. Illustrative.
M5Molds ordered (only if the numbers close)M4312027-01-152027-01-29+14yesQuote comparison, the numbers rerun, the decision and the order. Illustrative.
M6First articles approvedM5562027-03-152027-03-26+11yesEight weeks for the molds and the first parts. Illustrative.
M7First shipment to a distributorM6422027-04-302027-05-07+7yesSix weeks for the first run and packing. Illustrative.

Built by schedule.py from schedule.csv. Shaded rows are the critical path: the chain that sets the last date. A slip there moves the end; a slip elsewhere only uses up spare time.