Critical path: Buyer feedback from 3 distributors → Design frozen (risk actions in the CAD) → Molds ordered (only if the numbers close) → First articles approved → First shipment to a distributor.
The end moves: First shipment to a distributor is forecast 7 days after the charter's date. Recover time on the critical path, or the inventor accepts the new date through a change notice.
| ID | Milestone | Depends on | Days after | Planned (charter) | Forecast | Actual | Slip, days | Critical | Notes |
|---|---|---|---|---|---|---|---|---|---|
| M1 | Spring supplier confirmed | 2026-10-22 | 2026-10-22 | 0 | Waiting on the supplier | ||||
| M2 | Base mold quote in hand | 2026-10-29 | 2026-10-29 | 0 | Due from Molder A | ||||
| M3 | Buyer feedback from 3 distributors | 2026-11-30 | 2026-12-15 | +15 | yes | Illustrative: only one buyer meeting is set so far (10-28); two more distributors to approach | |||
| M4 | Design frozen (risk actions in the CAD) | M1 M2 M3 | 14 | 2026-12-15 | 2026-12-29 | +14 | yes | Two weeks after the last input to fold in the quotes and the buyer feedback. Illustrative. | |
| M5 | Molds ordered (only if the numbers close) | M4 | 31 | 2027-01-15 | 2027-01-29 | +14 | yes | Quote comparison, the numbers rerun, the decision and the order. Illustrative. | |
| M6 | First articles approved | M5 | 56 | 2027-03-15 | 2027-03-26 | +11 | yes | Eight weeks for the molds and the first parts. Illustrative. | |
| M7 | First shipment to a distributor | M6 | 42 | 2027-04-30 | 2027-05-07 | +7 | yes | Six weeks for the first run and packing. Illustrative. |
Built by schedule.py from schedule.csv. Shaded rows are the critical path: the chain that sets the last date. A slip there moves the end; a slip elsewhere only uses up spare time.