| supplier | quote ref | part number | part | tool type | cavities | tooling cost | piece price at volume | tool lead time | notes |
|---|---|---|---|---|---|---|---|---|---|
| Molder A | awaiting | MT-001 | Plastic base | steel; aluminum option asked | 1 and 2 (family) asked | Requested; quote due 2026-10-29 (A-001). Cost sheet still carries the $85,000 placeholder. | |||
| Molder A | awaiting | MT-002 | Trigger plate | steel | 1 asked | Requested; quote due 2026-10-29. Cost sheet placeholder $22,000. | |||
| Second molder | not asked yet | MT-001 and MT-002 | Step 3: pick a second and a third molder (the playbook asks for at least two). |
Readable copy built by record-view.py from the sheet of the same name. The sheet is the record.